Kingsferry Bridge: more problems

Following a recent report of the bridge operator refusing to lift for a yacht returning from Conyer to the Medway, the MSBA has sought clarification from Peel Ports. The bridge still has a problem with the main switch gear requiring a generator to be stationed on the A249 to enable lifts. Railtrack say they are “working hard” to source new parts to fix it, which is proving difficult. They have reduced the number of lifts to a minimum and are only allowing yachts through when there are shipping movements. We are told that commercial shipping takes priority.

UPDATE 6.2.2020: Network Rail expect to have the replacement switch gear in place within six weeks, possibly even sooner, so the emergency generator will no longer be needed. In the meantime boaters should check with the bridge operator on VHF channel 10, or Medway VTS on Channel 74, when the next bridge lift is expected to take place.