Improvement works to construct a concrete pad at the end of the access road to Commodores Hard has been delayed by one week owing to a high tide flooding the work site last week.
1st pour concrete happened on Wednesday 25th September and the next pour will be on Friday 27th October, after this, we must wait 2 weeks for concrete to cure (harden) before any vehicles can be parked on it.
Unfortunately, the access road will remain closed until 11th October.
Medway Council apologises for any inconvenience and thank you for your continued patience