Kingsferry Bridge – is your club intending to pass before end of May?

The bridge continues to be non-operational for leisure traffic due to the failure of Network Rail to replace the ancient motors. A temporary generator is only being used to lift for commercial traffic. Network Rail have told the MSBA that Kingsferry Bridge may not be fully operational until 25 April or potentially the middle of May.

Please advise Peter Norris (peter@msba.org.uk), of any rallies or events that are scheduled to take place between now and the end of May, which require passage through Kingsferry bridge, as he is working with Network Rail to find a solution so that the bridge can be navigated at weekends and Bank Holidays.

Kingsferry Bridge update

Network Rail have told us that, while work is being carried out to reinstate the power at Kingsferry Bridge, the bridge can only be lifted when there is a fitter on site, which is usually from 6am to 6pm Monday to Friday.  Outside these hours, leisure craft will only be allowed through with commercial vessels. Because of the compromised state of the equipment at the bridge, the risk of failure is higher than normal. Failure would result in the closure of the bridge to trains, road vehicles and prevent it being lifted.  If a fitter is on site, it can be reinstated quicker than if an on-call fitter must be called in.

Effectively then, Kingsferry Bridge will be out of action for the next three weekends and only available from 06:00 to 18:00 Monday to Friday.

Kingsferry Bridge: more problems

Following a recent report of the bridge operator refusing to lift for a yacht returning from Conyer to the Medway, the MSBA has sought clarification from Peel Ports. The bridge still has a problem with the main switch gear requiring a generator to be stationed on the A249 to enable lifts. Railtrack say they are “working hard” to source new parts to fix it, which is proving difficult. They have reduced the number of lifts to a minimum and are only allowing yachts through when there are shipping movements. We are told that commercial shipping takes priority.

UPDATE 6.2.2020: Network Rail expect to have the replacement switch gear in place within six weeks, possibly even sooner, so the emergency generator will no longer be needed. In the meantime boaters should check with the bridge operator on VHF channel 10, or Medway VTS on Channel 74, when the next bridge lift is expected to take place.

Revenge wreck about to collapse

Wreck of Revenge

Derek Meadows has sent us this photo of what remains of the notorious “pirate ship” Revenge, which mysteriously burnt after coming adrift in Faversham Creek. The steel structure is only held on by the stern. Derek fears that the wreck may topple and block the narrow navigable channel. He has contacted Peel Ports with his concerns but not yet had a reply.

Previous items about Revenge…

Obstruction outside Chatham Marina (GONE)

Peel Ports have advised that a craft work cradle/tray has sunk at the downstream end of Chatham Maritime Marina holding pontoon. The object is approximately 22m in length and is not visible at any state of the tide. The wreck has been marked with an orange pellet buoy, the owner is aware and will be dealing with the situation. Mariners should navigate with caution due to this submerged danger to navigation until further notice.

Note that the Chatham Marina lock is closed for annual maintenance until 26 January.

UPDATE 22.1.2010 The submerged obstruction has now been raised and is secured alongside at the Chatham Maritime Marina waiting pontoon. The owner will be moving it back to his yard over the next few days.

GridLink cable will pass through Medway Estuary

Route of GridLink high voltage cable.

GridLink Interconnector Limited (GridLink) is proposing to develop a high voltage direct current interconnector linking the British and French electricity grids. The GridLink project will consist of two converter stations, one close to the existing National Grid 400kv substation at Kingsnorth and one near Dunkerque. The converter stations will be connected by underground cables (onshore) and subsea cables (offshore).

Intertek has been appointed by GridLink as Marine Consultants to support the development of the project. GridLink is intending to submit an application for a Marine Licence (to the Marine Management Organisation) for the construction, operation and maintenance of a new electricity interconnector under the Marine and Coastal Access Act 2009, in May 2020. In support of the Marine Licence application, GridLink will provide environmental information and an assessment of potential environmental effects. For example, the application will demonstrate that due consideration has been given to navigational safety, the historic environment, effects on nature conservation sites (e.g. marine protected areas) and effects on other marine stakeholders (e.g. recreation and fishing). [Webmaster’s emphasis]

Intertek is currently preparing an Environmental Report to support the Marine Licence application. This will provide a baseline for each environmental topic; describe the likely effects of the proposed development on each topic, including identifying those that are potentially significant; and if necessary outline project-specific mitigation to be followed to avoid or negate adverse effects.

Stakeholders and the public will have the opportunity to review and comment on the Marine Licence application through a consultation exercise once the application is submitted. However, Intertek would like to ensure that the application documents address any concerns that stakeholders have prior to this consultation process.

Further information on the GridLink project can be found here. Intertek would welcome any questions and/or concerns regarding the project for consideration in the preparation of the Environmental Report, particularly from clubs or organisations close to the proposed route. From experience in the Thames Estuary, the MSBA is concerned that the works may require exclusion zones that may block access in or out of Stangate Creek for instance, affecting several clubs. The information supplied does not give reassurance on this point.

Comments can be provided by letter or email to the following address:
Anna Farley, Intertek, Exchange House Liphook, Hampshire, GU30 7DW
Email: Anna.Farley@intertek.com
Tel: 01428 727800

New MSBA Visitor Charts and Official Tide Tables

The MSBA has published a third edition of the Medway and Swale Visitor Charts. This time Gavin had the brainwave of including visitor moorings, slipways and fuel berths in addition to general updating.

What’s more, Peel Ports London Medway (yes really) have just published Official 2020 Tide Tables for Sheerness and Chatham. Print them off and don’t forget to add an hour for BST come next summer.

Find these and other useful free stuff on our Downloads Page